PROJECT WORKFLOW 2022

PROJECT WORKFLOW 2022

01

PHASE ONE: 

PRE-DESIGN

  • Conduct Location Research

  • Get Concept Ideas based on the communication with clients.

  • Client’s Space Specs review

  • Files and Drawings review

  • Design Timeline Setting (The design timeline would be set from the day of receiving the proceed notice from the client) (meeting required)

  • Contract

02

PHASE TWO: 

PLAN DESIGN

  • Concept Demonstration

  • Confirmation of the Design Concept to Client (meeting required)

  • Concept Rendering: Enhancing on Main Layout plant; Analysis plan; Zoning plan; Bird’s eye view; Perspective view.

  • Main terrain changes adjustment plan(Elevation, Section)

  • Main Plant & Tree Effect Picture

  • Demonstration on Main Design Plan (meeting required)

  • Consensus on Landscape Design Plan (w/client) ,

  • Finalize Main Layout Plan

  • Finalize Plant & Tree list

  • Section Amplifying Design

  • Floor Paving and Material adjustment

  • View Wall; Planting Pond, Doorstep, and Path Design

  • Fountain/Waterscape and Surface Material Design

  • Techniques Preparation

  • Facility Design

  • Landscape Lighting Design

  • Greening and Watering Setting Design

03

PHASE THREE: 

CONSTRUCTION DRAWINGS

  • Design Drawings Index

  • Layout Drawings

  • Design Plans

  • Elevation Drawings

  • Plants And Specifications

  • Lighting And Irrigation System(Additional Charge If Needed)

  • Section Layout

  • Section Plans

  • Enlarged Section Details Design Drawing

  • Section Renderings

  • Pavers Design Drawing

  • Structural Drawing

  • Electrical And Plumbing Drawings (Additional Charge If Needed)

  • Description Of The Design

  • Project Scheduling

  • Submittal Of Project Blueprint(meeting required)

04

PHASE FOUR: 

CONSTRUCTION COOPERATION

  • After the construction drawing and design is completed, the pre-construction design disclosure shall be made;

  • Confirm and seal the main paving materials selected by the construction unit to ensure that the landscape project is constructed according to the drawing;

  • Coordinate the main construction nodes to the site;

  • Assist the construction party to solve the technical problems arising in the construction of the project, answer the design problems of the construction unit, and be responsible for design changes;

  • Participate in the acceptance of all garden-related projects and issue completion approval.